Payload monitoring comparison
09605994 ยท 2017-03-28
Assignee
Inventors
Cpc classification
G06Q10/06393
PHYSICS
G01G19/64
PHYSICS
International classification
G06Q10/06
PHYSICS
G06Q40/00
PHYSICS
G01G19/64
PHYSICS
Abstract
Real time monitoring and comparison of bucket payload and truck payload during a loading process allows calculation of material lost in transfer between the loader and the truck. The lost or spilled material represents increased costs due to additional trips of the loader to fully load trucks and also in non-value added worksite cleanup time. The payload monitoring system can not only evaluate the mass of material lost over a period of time but can also calculate the value of that lost material using real time commodity pricing. The period of time can range from a single bucket dump to a workshift or longer. Payload masses and/or calculated values may be communicated directly between vehicles or may be communicated in conjunction with a central station.
Claims
1. A system for use in measuring material lost during vehicle loading at a worksite, the system comprising: a loader having a bucket; a bucket payload monitor that reports a first payload mass of the material delivered via the bucket of the loader; a truck configured to carry the material; a truck payload monitor that reports a second payload mass of the material loaded onto the truck via the bucket of the loader; and a controller configured to: subtract the second payload mass from the first payload mass to generate a lost payload mass, receive a commodity value of the material, and provide a business metric using the lost payload mass and the commodity value.
2. The system of claim 1, further comprising a reporting system that generates the business metric using the lost payload mass and provides the business metric to the controller.
3. The system of claim 1, wherein the business metric is a monetary value of the lost payload mass.
4. The system of claim 3, wherein the monetary value of the lost payload mass is calculated at the controller as a function of the commodity value of the material and the lost payload mass.
5. The system of claim 4, wherein the commodity value of the material is based on a real-time commodity price of the material.
6. The system of claim 1, wherein the business metric is a calculated number of extra trips, a time to clean up the lost payload mass at the worksite, or a cost of operating the loader during the calculated number of extra trips and cleanup time.
7. The system of claim 1, wherein the controller is part of a payload control system of the loader and the second payload mass is reported via a wireless network to the loader.
8. The system of claim 1, wherein the business metric is reported at an operator display of the loader.
9. The system of claim 1, wherein the controller is part of a central station and the first payload mass is reported via a wireless network from the loader to the central station and the second payload mass is reported via the wireless network from the truck to the central station.
10. The system of claim 1, wherein the controller is configured to calibrate a first test mass of the material delivered via the bucket and a second test mass of the material received at the truck under a no-lost payload mass loading condition.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1)
(2)
(3)
(4)
(5)
DESCRIPTION
(6)
(7)
(8) Similarly, the truck 110 may report truck payload amounts corresponding to a particular delivery of material 114 via the bucket 104 using a wireless link 136 to the central station 132.
(9) The central station 132 may use the bucket payload mass and the truck payload 112 mass to arithmetically arrive at a mass of the lost material, such as lost material 116 (e.g., spillage) of
(10) In an embodiment, the central station 132 may have a commodity price of the material, for example, that may be received via a satellite 138 or other network service. The commodity price may be used to calculate a value of the lost material. Additionally, the mass or even the volume of the lost material may be used to calculate an approximate cleanup time, using for example, a number of minutes per cubic yard for cleanup multiplied by the cost per minute to operate the loader 102 and/or other vehicles used in the cleanup.
(11) Any or all of the values for lost material mass, lost material value, and cleanup costs may be sent from the central station 132 to the loader 102. In some cases, such as where a truck driver may have a direct involvement in material spills, for example, moving before loading is complete, the truck 110 may also display one or more of these values.
(12)
(13) To illustrate further using a specific embodiment, the loader 102 may have a bucket 104 that carries 10 cubic yards of material. For dry gravel, a mass of 10 cubic yards may weigh about 26,700 pounds. If 26,100 pounds of payload gravel are received at the truck 110, simple subtraction says that 600 pounds of material was lost in the transfer, assuming good calibration between loader 102 and truck 110 and minimal errors measuring the respective masses. If gravel sells for $28 per ton, the value of 600 pounds is about $8.40.
(14)
(15) The controller 170 may send and receive data via a communication port 178. Sensor input block 180 may receive information from a variety of sensors, including one or more strain gauges, lift cylinder position sensors, and/or hydraulic pressure sensors (not depicted) for use in determining bucket payload mass or truck payload mass.
(16) The memory 172 may be any combination of volatile and non-volatile memory, including rotating media, flash memory, conventional RAM, ROM or other non-volatile programmable memory, but does not include carrier waves or other propagated media. The memory 172 may include an operating system 184 and utilities 186, such as diagnostic routines, etc. The memory 172 may also include executable code and data, such as a lost load monitor module 188 and data storage for values, such as but not limited to, bucket payload mass 190, truck payload mass 192, lost mass 194, cumulative values 196, such as cumulative lost mass and cumulative value of lost mass, and commodity prices 198 used for calculating value.
(17) The controller 170 is an illustration of one embodiment for implementing the payload monitoring comparison. In other embodiments, the functions supported by the controller 170 may be arranged differently, spread between processing units in separate vehicles or controls stations, or maintained in a cloud service remote from the worksite 100, to name a few variations.
INDUSTRIAL APPLICABILITY
(18) The ability to track lost material during loading provides a valuable tool for improving productivity and for operator training and real time feedback. A worksite manager gets valuable information in the form of business metrics about the operation and can use these business metrics to improve conditions that may lead to more accurate loading, such as more consistent location of trucks 110 or position guidance for loaders 102.
(19) These business metrics may include lost material per shift, worksite cleanup time costs, additional loader work cycles (extra trips) due to lost material, the operating expense of both the cleanup operation and the additional loader work cycles, etc.
(20)
(21) At block 204, the truck payload mass is then received at the controller 170. The truck payload mass may be developed at the truck by any number of known mechanisms including strain gauges. Alternatively, the truck payload may be developed externally using a worksite scale and a standard weight before loading subtracted from weight after loading.
(22) At block 206, the truck payload mass may be subtracted from the bucket payload mass to calculate a lost material mass.
(23) Optionally, at block 208, a commodity value of the material may be received at the controller 170. As discussed above, the commodity value may be stored in the controller 170 at the beginning of a shift or for highly volatile commodities, may be received on a regular basis via a network or broadcast feed.
(24) In conjunction with block 208, optional block 210 may provide for calculation of a monetary value of the lost material mass by multiplying the lost material mass by the value of the material per unit.
(25) At block 212, the cumulative lost material mass, lost material value, or both, may be recorded in a local memory, a remote memory, or via hardcopy. At block 214, the lost material mass, its value, or both may be presented in real time at an operator station in the loader 102 or at a dispatch or other console at the central station 132. As discussed above, the ability to present lost material information provides timely feedback for both loader operators and worksite managers to improve efficiency and lower costs.
(26) In accordance with the provisions of the patent statutes and jurisprudence, exemplary configurations described above are considered to represent a preferred embodiment of the invention. However, it should be noted that the invention can be practiced otherwise than as specifically illustrated and described without departing from its spirit or scope.